Programme · 60×60
04 Programme

Seventeen months, five gates

Ten weeks of preliminary work and fifteen months of implementation, shown in relative months. No calendar start date, funding milestone or permit completion date is established.

Indicative sequence

Relative months from authorisation. Overlap, procurement lead times and seasonal survey windows must be integrated before any date is issued.

  1. Bathymetry and current mapping. The survey defines what the design is allowed to assume.
    F01W1–W10

    Studies and definition

    Oceanography, bathymetry, seabed, environmental scoping, route constraints and configuration selection.

  2. Cross section of the assembly concept. Calculations resolve dimensions, draft and load path.
    F02M2–M5

    Design and modelling

    Transport and interaction modelling, structural and mooring calculations, navigation integration, draft specifications.

  3. Alignment across the Cozumel Channel. Consultation and permits fix where segments may actually sit.
    F03M3–M6

    Approvals and consultation

    Environmental assessment route, authority engagement, marine users, consent dependency register.

  4. Fabrication of barrier elements. First article tests gate the rest of the order.
    F04M5–M9

    Procurement and fabrication

    Supplier qualification, first article tests, module fabrication at 120 m elements, quality records.

  5. Pipes prepared for towing. Installation is staged so early results inform later placement.
    F05M9–M15

    Marine installation

    Shore base, towing, anchoring, segment commissioning, staged so early results inform later placement.

  6. Multi-sensor monitoring. Handover requires a measured baseline, not a declared one.
    F06M15–M17

    Commissioning and handover

    Integrated testing, operator training, performance baseline, as-built records and open items.

Decision gates

GateRelease evidencePrincipal dependency
Concept selectionSurvey plan, alternatives, route constraints and initial feasibilityAccess to historical engineering and baseline data
Design freezeChecked calculations, drawings, environmental and navigation integrationAdequate observations and resolution of critical assumptions
Procurement releaseApproved specifications, quantities, quality plan and commercial scopeFunding authority and defined treatment of long lead risk
Installation releaseRequired approvals, accepted components and qualified marine proceduresPermits, vessels, shore base and a suitable weather window
Operational acceptanceCommissioning evidence, trained team and agreed performance resultsComplete records and closure of critical defects

Each gate releases the next commitment only when its evidence exists. A gate is not a date; it is a condition.

Two reconciliation notes

Approvals must not trail the decisions that depend on them

The source schedule places environmental processing in months 3 to 6. If approvals arrive after procurement or installation decisions, the programme absorbs redesign or stands down. Scoping and navigation engagement should begin during concept development.

Different commitments, different durations

A technical effort of roughly three months and a commercial aspiration of five months address narrower work than physical delivery. They do not replace the approximately 17 month installation programme and should be reported separately.

Construction and assembly of barrier elements. Fabrication capacity constrains the installation sequence more than the calendar does.

The useful output of this phase is not a date. It is a package that supports a clear proceed, revise or stop decision.