Studies and definition
Oceanography, bathymetry, seabed, environmental scoping, route constraints and configuration selection.
Ten weeks of preliminary work and fifteen months of implementation, shown in relative months. No calendar start date, funding milestone or permit completion date is established.
Relative months from authorisation. Overlap, procurement lead times and seasonal survey windows must be integrated before any date is issued.
Oceanography, bathymetry, seabed, environmental scoping, route constraints and configuration selection.
Transport and interaction modelling, structural and mooring calculations, navigation integration, draft specifications.
Environmental assessment route, authority engagement, marine users, consent dependency register.
Supplier qualification, first article tests, module fabrication at 120 m elements, quality records.
Shore base, towing, anchoring, segment commissioning, staged so early results inform later placement.
Integrated testing, operator training, performance baseline, as-built records and open items.
| Gate | Release evidence | Principal dependency |
|---|---|---|
| Concept selection | Survey plan, alternatives, route constraints and initial feasibility | Access to historical engineering and baseline data |
| Design freeze | Checked calculations, drawings, environmental and navigation integration | Adequate observations and resolution of critical assumptions |
| Procurement release | Approved specifications, quantities, quality plan and commercial scope | Funding authority and defined treatment of long lead risk |
| Installation release | Required approvals, accepted components and qualified marine procedures | Permits, vessels, shore base and a suitable weather window |
| Operational acceptance | Commissioning evidence, trained team and agreed performance results | Complete records and closure of critical defects |
Each gate releases the next commitment only when its evidence exists. A gate is not a date; it is a condition.
The source schedule places environmental processing in months 3 to 6. If approvals arrive after procurement or installation decisions, the programme absorbs redesign or stands down. Scoping and navigation engagement should begin during concept development.
A technical effort of roughly three months and a commercial aspiration of five months address narrower work than physical delivery. They do not replace the approximately 17 month installation programme and should be reported separately.
The useful output of this phase is not a date. It is a package that supports a clear proceed, revise or stop decision.